Sanitary Sewer System


Message from the City Engineer (8/22/11)

Residents in the area of current sewer system development will receive a letter from the Lake County General Health District formally ordering them to connect to the sewer.  Even prior to that, residents are free to start that process by contacting the City’s Building Department for information on how to proceed.


 

Sewer "area C" residents workshop (June 14th, 7:00pm)

  • The City hosted a workshop for residents in the new sewer "area C" to assist them in making the connections to the sewer.
  • Engineers, contractors and representatives from local banks were present to assist residents and answer any questions about the sewer connections and assessment payments. 
  • The event was held at the Community Center on Tuesday, June 14th at 7:00pm

Sewer system update (as of 4/29/11)

  • Pavement work and final restoration (grading, topsoil dressing and seeding) has begun and will continue through June.  Final work is being performed to ensure proper operation of the pump stations on White Road and Tall Tree Trail.  
  • The final contract completion date is June, 2011.
  • Residents were notified of an option to make a partial payment on the assessment with a deadline of May 9, 2011. 
  • We also are notifying everyone who is considering a consolidation of lots you own that a deadline of May 31, 2011 is established as the final date for which the City can consider prior to preparing the final assessment.
  • Please be advised that final assessments are expected to be issued to each property owner in early July.  The notice will explain and outline your options for payment.

The City extends its gratitude to everyone affected by this project and thanks you for your patience.

Sewer system update (as of 12/22/10)

  • Sewer and laterals are complete on Bishop Road, Willow Lane, Lynn Drive, Cricket Lane, White Road East (Erich to Lynn), Erich Drive, and Canterbury Court.  Paving operations are complete on Willow Lane, Lynn Drive, Cricket Lane, White Road East and West, Bishop Road, Erich Drive, and Canterbury Court.
     
  • Pavement work and restoration will continue in the Spring on Eddy and Rockefeller Roads; and, Tall Tree Trail.
     
  • Mainline sewer installation is completed on Eddy Road, Rockefeller Road, and Sayle Drive.   Sewer lateral work will continue through January and February of 2011.  Work is now underway to install the sewer and pump station on Tall Tree Trail.

The Contractor is anticipating that all sewers will be installed by the end of January, 2011.  The contract requirement is to have all the sewer lines installed and accepted for use by March, 2011. The final contract completion date is June, 2011.

Restoration will not be completed this year, so please be patient.  There is work yet to be done to meet the contract requirements.  Please continue to maintain the restored area.  The City expects the Contractor to remobilize in the Spring to address settlement, grading and weed control.  

Thank you for your patience.   
 

Sewer Assessment Area "C" residents meetings (updated 5/13/10)

The City conducted meetings for residents in Sewer Assessment Area "C" to discuss the installation procedures for sewer connections.  The meetings were held at 6:30pm on Monday, May 10th and Wednesday, May 12th at the Community Center.

Click here to view or download the packet of material that was distributed at these meetings.


Euclid Creek Tributary Watershed Sanitary Sewers
Lateral Installation Program
MARCH, 2010

Background

 

Willoughby Hills is now in the third and final phase of providing sanitary sewer service for the western portion of the City that is part of the City of Euclid’s Sewer District.  Willoughby Hills has an Agreement with Euclid who provides wastewater treatment for this portion of the City.  This District includes the western side of the City extending south to the City’s corporation line and with an easterly limit at the City Hall complex and the Community Center on Chardon Road. 

 

Sewer construction is well underway and is scheduled to be completed in 2010 on the following streets:

 

  • White Road from just east of Bishop Road to the City’s westerly corporation limit
  • Bishop Road from just south of White Road north to the Creek
  • Tall Tree Trail
  • Lynn Drive and Cricket Lane
  • White Road from Erich Drive to just west of Lynn Drive
  • Erich Drive and a portion of Willow Lane
  • Eddy Road from just east of Orchard Drive to Rockefeller Road
  • Rockefeller Road from Eddy Road to I-90
  • Sayle Drive

Property owners will receive a written order from the Lake County General Health District upon completion of the City’s sewer project.  Owners must connect to the sewer within one (1) year of notification.  The City understands the burdens these requirements will place on the homeowners.  This lateral installation program was developed to provide assistance.


Installation Program

 

I.      As part of the first phase of this program, the City will advertise or solicit contractors who are interested in performing the work for the individual homeowners to an informational meeting.  The advertisement will be an invitation supported by some general information about the project and its schedule.  The informational meeting will help judge interest and capacity of the contractors to perform multiple installations.  The City of Willoughby Hills will not participate in any negotiations or enter into any contractual obligations with these contractors.  It remains the homeowner’s sole responsibility for this action.  The City will advise interested contractors on the specifications and permitting obligations for the installation process.  The City will schedule this program in advance of the completion of the project.

   

II.    The second phase will involve two (2) separate meetings with neighborhoods.  At these meetings, informational packets will be distributed.  Included in these packets will be a “cut-away” sketch of the new lateral to be installed, a copy of the City’s specification sheet, an explanation of the work to be done and a discussion of the cost of work.  The residents will be informed of the advantages of having work performed as early as possible so that only the final connections will be needed once the sewers are accepted.   A list of registered and interested contractors will be provided to the residents.  Please consider collaborating with your neighbors in order to negotiate a bulk price from Contractors.  It will be up to each neighborhood group to organize this effort.  The City will notify you of the time and date of these meetings at the Community Center.

 

III.   The third phase of this program will be the installation of your sewer lateral connection.  Once the sewer main has been accepted by the City, the Lake County General Health District will issue a notice of connection.  This notice will indicate one (1) year as the time period for connection.  The property owner will need to contract with a City-registered contractor who is required to post a bond with the City’s Building Department.  The homeowner or his/her contractor will contact the City’s Building Dept. to request an application for a sanitary sewer connection.  These applications will be available with the Building Dept. and they will specify the fees due to the City before any work is permitted to proceed.  Your contractor will be required to call for inspection at least 48 hours in advance of the work.  Once the sewer lateral has been connected, the City notifies the Lake County General Health District and the Lake County Utilities/Billing Department.  The City’s Service Dept. will perform a dye test to ensure that no clean water connections to the sanitary sewer are evident.

   

Additional information to assist property owners:

 

Please accept this as guidance on how to get your connection to the sanitary sewer done.

 

  1. The City will provide a copy of contractors who are registered with the City to perform the work.  Please review this list either individually and/or speak with your neighbors.  As noted, it may be advisable to select and hire a contractor as a group with neighbors on your street who will have the same requirements.  The advantage for you is to get a discounted price based upon the volume of work a contractor could have on your street.
       
  2. When you do speak with a contractor, request a list of references with names and phone numbers for you to contact to ask about their performance.  Research the background of contractors you consider with the Better Business Bureau.  Many of these contractors were probably involved in installing sewer connections for many of your fellow residents recently as part of the City’s other sewer projects.  Those streets already completed include Marcum, Parkview, Martin, Dixon, Emerald Lakes, Evergreen, SOM Center Road, Rockefeller Road, Eddy Road and Bishop Road.
     
  3. We are providing you with a “cut-away” sketch of the new lateral to be installed (attached at the end of this document) and a copy of the City’s specification sheet. 
     
  4. After review and research of these contractors, solicit a detailed quotation to perform the work and request that the contractor visit your property to examine and review where your lateral will be installed.  At a minimum, the City suggests the detailed quote include unit prices to install the pipe or lateral; the cost to properly pump out your septic tanks and abandon it; and the final restoration of your property with topsoil and seed or sod depending upon your individual needs.  
     
  5. If a deposit is requested, make sure it is reasonable.  Agree to only reasonable and measurable progress payments.  Insist upon completion and acceptance by the City before you make final payment.
     
  6. Your installation has to be free and clear of any connections from your footer drains, sump pumps, or downspouts.  The City will confirm that with the dye test when your Contractor has completed the job.

For a printer-friendly copy of this document, click here

 



Sanitary Sewer System Investigation & Detection Program (3/24/10)

The City began a methodical approach to ensure the proper operation and functioning of the City’s sanitary sewer system.  An investigation will be conducted annually for each neighborhood with sewers.  The City began with the Green Ridge neighborhood that includes Miller, Alan, Meadowbrook and Diane on the north side of I-90.  Corrections are being made both by the City and by property owners to ensure that only sanitary wastewater is connected and that the sewer system in general is sound.

The next phase of this program will be conducted this year on Camelot and Canterbury Courts.   Property owners will be notified of all activity in advance.

From the Summer/Fall issue of the Euclid Creek Watershed newsletter (September, 2009)
Willoughby Hills Improving Main Branch of Euclid Creek
Laura Kramer Kuns, LCGHD

The Lake County General Health District (LCGHD) conducted an extensive sewage pollution survey in the Euclid Creek Watershed that included sewage system tracing dye testing of household sewage treatment systems and water quality sampling for fecal coliform bacteria in the watershed. The survey began in 1996 and took over three years to complete.  In the spring of 2000, the LCGHD submitted the survey report to the City of Willoughby Hills summarizing the findings.  The soils in the Euclid Creek Watershed are silt loams with shallow shale bedrock, seasonal high water tables and very slow permeability.

 

The average age of the sewage systems in the watershed were between 30 to 50 years old. The results of the survey were as follows:

  • The sewage systems in the watershed were failing at rates between 50-66%
  • The water quality samples taken in ditches discharging into Euclid Creek and in the Creek itself ranged from 47,000 to 240,000 fecal coliform per 100 ml.
  • Most properties had limited area for on-site replacement sewage treatment systems.

The LCGHD report strongly urged the City of Willoughby Hills to take steps necessary to design, fund and construct sanitary sewers in the Euclid Creek Watershed.  The City in turn designed and constructed a main sanitary sewer truck line along the Euclid Creek corridor on White Road that is treated by the Euclid wastewater treatment plant.  The extension of the sanitary sewer through the various streets was developed in three phases. Two phases have been completed and the Health District has issued orders to 374 property owners to connect to the sanitary sewer and abandon their septic systems.  To date 315 have connected and the remainder have either received extensions for connection or are in the legal process.  Additionally, the City was able to eliminate several existing pump stations that were causing overflows during heavy rain events and the County was able to eliminate a package treatment plant that discharged to the creek.  The third phase of the sanitary sewer project in the watershed will be ready for connection in 2011 and involves approximately 280 additional properties.

 

The improvements to the watershed will be documented by follow up fecal coliform sampling at the completion of phase three of the project.  The improvement in the quality of the water in the drainage ditches in the completed areas is evident as there is no longer black, stinky water and sludge present in the water.

 

 

Area "C" sewer meeting (June, 2009)

The City held two townhall meetings for the residents in the current sewer project area, known as "Assessment Area C".  The purpose of these meetings was to present the plans and schedule for the current sewer construction project.  Representatives from the City Engineer's office, the City Administration and Council, and the Lake County General Health District, were present to outline the project details and answer questions. 

To view the PowerPoint presentation given at these meetings, click here

Financial Hardship
Property owners who demonstrate financial hardship can seek assistance through Lake County’s Department of Housing Rehabilitation. Assistance is available for the installation of the sewer connection only. Administrative costs and connection charges are not eligible.

Please contact Toni Marie Ciliberto, Lake County Housing Rehabilitation Manager, at (440) 357-4400 for assistance.


Project Manager: Richard Iafelice CityEngineer@WilloughbyHills-OH.gov
Building Dept.: Fred Wyss    Building@WilloughbyHills-OH.gov

 
 
 
Tornado Technologies
© City of Willoughby Hills, All rights reserved.